LB 1208 Timeline
The following is the Phase II installation timeline for distance education upgrades: (FYI - For your information with no action required)
Date
| Activity
| May
| Submit summer plan for assisting in Equipment and Network upgrade. | June
| Your School Board must approve and submit payment for CODEC/Cart orders and Router/Switch orders. | June 9,10,12,19,20
| CODEC distribution and training at ESU 10 (9th,10th,19th,20th) & ESU 11 (12th). Must have a school representative in at least one training to get your CODEC that is awarded as part of USDA grant.
| | June 15 or ASAP | Submit duplicate receipt payment copies to ESU 10 of equipment as evidence of in-kind contribution in support of the USDA grant. Submit by fax 308-233-9066 or by mail ESU 10 - POB 850 Kearney 68847
| June 30
| Member schools must complete Distance Education Reimbursement Report using Nebraska GMS. Click here to see a sample of evidence needed for payment documentation.
| July 1
| FYI - Official connection date for ESU 10/11 schools to Network Nebraska.
| July 1
| FYI - Upgrade of transport networks for STEPS and TVDEC north schools by IPS providers (NCTC & Qwest)
| July (TBD)
| ESU 10 staff will change out classroom equipment in STEPS and TVDEC north schools
| Sept/October
| FYI - Should receive reimbursement of LB1208 funds.
|
The documentation with links on this web page can be found at http://www.tvdec.org/LB1208timeline
This Page was last update: Thursday, May 22, 2008 at 4:08:09 PM
This page was originally posted: 5/20/08; 2:25:33 PM.
Copyright 2009 Tri-Valley Distance Education Consortium - TVDEC
This site is using the Adult Contemporary (red) theme.
Membership : Join Now : Login

|
|